S3 Company opens a second colocation hall

S3 Company opens a second colocation hall

Two and a half years after we opened our first colocation hall, it has filled up and the time has come to open a second one.

The new hall increases not only our colocation capacity but also the redundancy of the data center. It has its own modular UPS systems, its own generators and separate power cables, so the two halls do not share a power chain. The UPS modules can be replaced without interrupting power to the racks.

The hall is equipped with HP G2 48U racks. They are well suited for servers and have enough room for tidy cable management. Their doors are perforated, so air flows through them freely.

As standard, every rack has two 32A PDUs, each with 48 C13 sockets. That is 96 sockets in total. Even a rack filled to the top with 1U servers that have two power supplies each has a separate socket for every power supply, so the whole space can be put to full use.

Right after the opening we started moving client servers from another data center in Sofia into the new hall. For a migration like this, our team prepares the PDUs, power cables and fiber and copper patch cords in advance, so the machines are switched on as soon as they arrive. This is also how our Data Center Transfer service works.

The new hall has room both for new clients and for those who want to expand their equipment with us. If you are looking for space for your servers or a whole rack, see Server Colocation and Rack Colocation, or contact our team.

Share: S3 Company opens a second colocation hall S3 Company opens a second colocation hall